16 new-build permits in Skydra in the past 12 months, 0 in the last 30 days alone. With floor area, floors and uses straight from the permit.

Updated: (latest permit)

Live finding · 13 November 2026

Building permits of all types in Skydra are down 15% on the same period last year.

17 permits between 13 October 2026 and 11 November 2026, against 20 in the same weeks a year earlier.

The numbers in Skydra

New-build permits, 30 days
0
New-build permits, 12 months
16
New builds with 3+ floors
3
New permits with a pool
0
New floor area (m²)
9,871
Building permits, 7 days
3
Building permits, 30 days
13
Building permits, 12 months
260

12 months unless stated. Building permits = new builds, small-scale works, revisions and pre-approvals.

Nov 2025: 1Nov2025Dec 2025: 2DecJan 2026: 1Jan2026Feb 2026: 1FebMar 2026: 33MarApr 2026: 1AprMay 2026: 1MayJun 2026: 2JunJul 2026: 2JulAug 2026: 0AugSep 2026: 1SepOct 2026: 22OctNov 2026: 0 (month to date)0Nov
New-build permits per month; the current month to date, lighter.

By permit type, 12 months

  • New builds16
  • Small-scale works198
  • Revisions35
  • Pre-approvals11

What is being built in Skydra

Over the past 12 months, 16 new-build permits were issued in Skydra, out of 260 building permits of all types (including small-scale works, revisions and pre-approvals). That is 33% fewer than in the previous 12 months (24). Together they add 9,871 m² of new floor area (counting the 9 permits that state it).

25% of the new buildings have three or more floors.

Skydra accounts for 11% of new builds in Pella and ranks 4th of 4 municipalities.

Where Skydra stands

#12 months30 days
1Pella767
2Almopia322
3Edessa254
4Skydra160

The latest permits in Skydra

The most recent new-build permits and pre-approvals. Address, cadastral ID and engineers are inside Bouldoza.

Latest permits.xlsx
DateTypeMunicipalityFloorsm²UseAddress & engineer
14 October 2026New buildSkydra—15Residential
13 October 2026Pre-approvalSkydra1608Industry and manufacturing
1 October 2026New buildSkydra31,131—
24 September 2026New buildSkydra1141Residential
22 September 2026Pre-approvalSkydra31,514Residential, Parking and fuel stations
27 July 2026Pre-approvalSkydra23,923Industry and manufacturing
9 July 2026New buildSkydra5588—
3 July 2026New buildSkydra14,263Industry and manufacturing
address & engineer — in Bouldoza

Who it's for

Lifts and elevators

3 new buildings with three or more floors in the past year: the likeliest customers for a lift.

All of Pella

Windows and doors

16 new builds and 9,871 m² of new floor area. Every one of them will need windows and doors.

All of Pella

Swimming pools

0 new permits with a swimming pool in the past year, with the engineer who designed it.

All of Pella

Building materials

9,871 m² of new floor area in 16 permits: where cement, bricks and steel will be needed.

All of Pella

Electricians and solar

16 new builds and 198 small-scale works, from refurbishments to solar panels.

All of Pella

Frequently asked questions

How many new-build permits were issued in Skydra in 2026?

14 from 1 January to 13 November 2026. In the same period of 2025 there were 21, and 23 in the whole of 2025.

How many new apartment buildings are going up in Skydra?

In the past 12 months, 3 new-build permits were for buildings with three or more floors, 2 of them with four or more. We count the 12 of 16 permits that state the number of floors.

How does Skydra compare with other municipalities in Pella?

It ranks 4th of 4 for new-build permits over the past 12 months, with 11% of the total. The top three are Pella (76), Almopia (32), Edessa (25).

How many new permits with a swimming pool were issued in Skydra?

0 in the past 12 months (new builds and small-scale works), 0 in the last 30 days. We only count permits that explicitly mention a pool, so the real number can only be higher.

Where can I see the address and the engineer for each permit?

In Bouldoza: every permit with its address, cadastral ID (KAEK), engineers and location on the map. You can ask for the latest 10 permits in Skydra for free with the form on this page.

Where does the data come from and how often is it updated?

From the e-Adeies building permit system, as published on Diavgeia, the Greek government transparency portal. This page updates itself several times a day; the latest permit in Skydra was issued on 9 November 2026.

10 free permits for your area

Tell us what you do and we will email you the 10 most recent permits in Skydra: what is being built, how many m², how many floors, exactly where and which engineer designed it.

One time, no subscription, no account needed.

We use your details only to send you the permits and reply to you. You are not added to any mailing list. Privacy